St. Francis' new worship home is on its property located at 1484 Hockett Road near Centerville, Virginia. We are 1/2 mile south from the intersection of Broad Street and Rt 623 Hockett Road. St. Francis is easily accessible from exit 173 off of I-64, from Tuckahoe Creek Parkway, off Rt 288, and from Rt 6 River Road West via its intersection with Hockett Road.
During our first 6.5 years, St. Francis held its worship services in several locations, the last being the Randolph Elementary School. Construction on the new facility began on August 16, 2010 and completed on December 5, 2010. It involved renovating the existing building on the church property into a Parish Hall which allowed the congregation to begin worshipping on our own property in our own building. Please join us for worship in our new home and take a photographic tour of our "Renovation Journey" below:
Existing building prior to work beginning |
|
|
|
Building After Member Demolition |
|
Contractor Progress Photos |
|
8-29-2010: | Chimney removed, ceiling raised, interior studs removed, foyer and bathroom built out, plumbing pipes installed, floor reinforced, driveway / parking lot work begun |
9-02-2010: | HVAC ductwork installed, electrical cables and boxes being installed, music speaker and amplifier cables installed, driveway gravel being placed |
9-14-2010: | Bushes removed in front of house, driveway graded and graveled, outside windows sealed, sidewalk being poured, backyard fence posts removed, old porch brick steps removed |
|
|
9-27-2010: | New sidewalk completed, insulation installed, deck partially complete, new exterior doors installed, windows and doors wrapped |
9-28-2010:
|
Siding installation begun, additional progress on deck
|
|
|
10-01-2010: | Continued to add siding, sheetrock installation begun, front deck completed |
10-13-2010: | Siding completed, sheetrock completed, painting completed, trim and cabinet installation begun, back deck completed. |
10-17-2010: | Trim and cabinet installation completed, floor installation begun |
10-24-2010: | Floor Installation completed, kitchen, bathroom, and plumbing fixtures installation completed |
10-28-2010: | Mobile building installed, electrical fixtures installation begun, HVAC installation and fixtures begun |
11-21-2010: |
Electrical fixtures installation complete, HVAC installation complete, new utility room stairs installed, utility room and narthex doors installed, outside cross installed, mobile building deck installed |
12-05-2010: | Parking lot paving, barrier, and signage installation completed. Occupancy permit received |